Setting up construction-site power starts with a plan for where it is needed and which equipment will operate together. The pole is the connection point; the wider site's electrical distribution also needs assessment by a licensed electrical contractor.
This guide covers site planning. For applications and provider appointments, use the Energex connection process guide.
Map the work areas
Mark the site office, trade work areas, access routes and the changing building footprint on the plan. Identify where equipment will be used at each construction stage. A pole position that works before excavation may later conflict with a delivery route or scaffold.
Send the plan and access photos with your temporary-pole enquiry. We review the proposed pole configuration and installation position before scheduling.
Have the electrical demand assessed
Give the electrical contractor the equipment schedule and expected simultaneous use. Confirm single-phase or three-phase requirements and the required outlets. Do not choose from a building's floor area alone or assume every tool can share one outlet.
The contractor should design any site distribution beyond the supplied pole for the actual work. This article does not provide cable sizing, wiring or connection instructions.
Keep power and vehicle routes separate in the plan
Ask the responsible contractor to review how electrical equipment will be protected from site traffic, water and construction activity. Revisit that plan when work areas move. Do not run a lead or alter equipment simply because a previous stage used the same route.
The stayed-pole footprint must also remain clear. Its support dimensions are different from electrical-line exclusion requirements; nearby scaffold or crane work needs a separate safety assessment.
Confirm responsibilities before work starts
Record who arranges the connection application, agreed electrical work, EWR, retailer account, network connection and metering. Confirm the person responsible for ongoing inspections and test records. Keep these contacts available to the site supervisor.
Installation of the pole does not confirm that the supply is live. Wait until the responsible providers confirm the required connection and energisation work is complete.
Review the setup during construction
Tell us about changed access, excavation near the pole or damage to the supports. The responsible electrical contractor should review changes to equipment or distribution needs. Keep materials and vehicles away from the pole and maintain access to its box.
Use the site checklist to track these planning tasks. For minimum hire, delivery and equipment options, return to temporary power pole hire.