Temporary Power Pole Hire Duration and Off-Hire

Summary

Understand the 12-week minimum, continued hire, connection planning and the steps needed before a temporary pole can be collected.

DougOwner & Director

Published 19 August 2022 · Updated October 2026

On this page
  1. What if I only need it for a few weeks?
  2. Can I keep the pole longer than 12 weeks?
  3. When should I plan the permanent connection?
  4. How do I finish the hire?
  5. What if there will be no permanent supply?
  6. What should be recorded in the quote?
  7. Questions
photo of side of building on a construction site

A temporary power pole is hired for the period your project needs a temporary supply, subject to the agreed hire terms and ongoing site requirements. Our minimum hire is 84 days, or 12 weeks. It is a minimum charge, not an automatic collection date or a promise that every build will be finished by then.

For current equipment prices and the selected configuration, use temporary power pole hire.

What if I only need it for a few weeks?

The minimum hire charge still applies. Compare that cost with the actual power needs and planned duration of the project before booking. Network and metering arrangements also take planning, so a short period of use does not necessarily mean an immediate connection.

Can I keep the pole longer than 12 weeks?

Contact us to confirm continued hire, the applicable rate and any changed site conditions. Do not assume that extending the hire removes inspection or testing duties. The people responsible for the site must maintain the required checks throughout the hire.

If the build programme changes, tell us the revised date and review the pole position against upcoming work. Stays, access and the service route must remain suitable as the building develops.

When should I plan the permanent connection?

Discuss it with your builder or licensed electrician before the temporary supply is no longer needed. Equipment installation, network work and metering are separate stages. Do not schedule pole removal solely from the expected completion of internal building work.

Our temporary and permanent pole comparison explains the different products. A temporary hire pole is not automatically converted into a purchased permanent pole.

How do I finish the hire?

Contact the responsible providers to arrange safe transfer or disconnection of the temporary supply. The service wires and meter must be removed as required before the pole can be collected. Then contact us to confirm off-hire and the collection appointment.

Ask us to confirm the effective off-hire date. Do not infer it from the day you stop using electricity, the minimum term ending, or an expected pickup date. Keep the collection route clear until the visit is complete.

What if there will be no permanent supply?

Ask your retailer about the required disconnection or supply-abolishment process for the address. Once the temporary supply is safe for removal and the required equipment has been removed by the providers, arrange collection with us. Never disconnect or remove the pole yourself.

What should be recorded in the quote?

Confirm the minimum term, ongoing rate, agreed installation scope and off-hire process. Keep those details with the connection references so the person finishing the project can arrange removal without guessing who is responsible.

About the author

Doug, Owner & Director

Doug and Deb purchased Poles and Holes in 2002 as its third owners. Doug is the owner and director of the Capalaba business, which was established in 1960 and supplies temporary power poles, portable toilets and site security cameras.

Frequently asked questions

Will the pole be collected automatically after 12 weeks?
No. Contact us to confirm off-hire and collection after the temporary supply is safe for removal. The 12-week period is the minimum hire, not an automatic pickup date.
Does finishing early reduce the minimum charge?
No. The 84-day minimum charge applies even when the pole is used for less time.
Can hire continue while permanent power is delayed?
Contact us to confirm continued hire and the applicable rate. Maintain the required site safety checks and keep the pole and access area clear.

Need temporary power on site?

Send us the site address and start date. We’ll confirm the pole, the Energex paperwork and the delivery fee.